Schedule Logic
Forum TopicAll,I am reviewing a P6 schedule submitted by a Subcontractor, the schedule has;6,793 total activities which includes;512 date constraints463 activities without predecessors126 activities without successors1 activity on the Longest PathIn the Contrac...