Primavera P6 V7 adding user for specific period only

Forum Topic

Hello planners!!Need help releated to adding user in primavera P6 v7is that possible to add an user for specific period only for e.g.I want to add one user form suppose 10th Dec 2012 to 31st Dec 2012is this is possible to do if yes! how?Thank you wel...

Dec 20, 2012

Display Calender days

Forum Topic

Gday A simple question which has already been answered in previous posts however i thought I might ask again. Can I display a calender days column. Activity #1 has 90 working days, which is how many calender days.......... Without using global change...

Dec 21, 2012

LOE activity updating resource units

Forum Topic

Hi,I am using P6 v7.I have a Level of Effort activity with pred and successors.When I update the pred the LOE not taking the actual values.The resource labor units not updating.I am using Duration % complete.Regards,kp

Dec 23, 2012

Phone interview

Forum Topic

 if u have technical interview in phone as a Plannig Engineer , what kind of quis. may u faced ??

Dec 23, 2012

Activity code gets reused, when last activities are deleted

Forum Topic

Hi,I was looking at comparison of different versions of schedule and found one issue, which I would consider a bug, unless I miss something.Every task in Spider has a code field, which Spider later used to uniquely identify task, when comparing diffe...

Dec 24, 2012

Working with phases (summary tasks) n Spider

Forum Topic

Vladimir, Rafael,I am looking now at phases and I have the following few questions:Question 1I could not find any function similar to “Indent” or “Outdent”, available in MSP or Asta. I only found “Convert to Phase”. Hence the only way  I found to Ind...

Dec 25, 2012

impact analysis using P6

Forum Topic

Dear all,My project is reaching 72.20% this week(data date 21-Dec-2012). and our contract project Mechanical Completion date is 30-Apr-2013. now, we are ahead of schedule(bl Cum 65.53%). however, there are some problems:for many Procurement items, Pr...

Dec 26, 2012

Working with Scripts

Forum Topic

Hello,First of all I have to say I have little experience working with Spider Project. I have been trying to create scripts in order to perform complex tasks faster when I hit a dead end trying to create a script for risk analysis. The script looks l...

Dec 27, 2012

Global Code Change over Multiple Projects

Forum Topic

I have 142 projects in my T&D Program! I need to import a global code change to identify seperate engineering packages. Currently all my P&C packages have one code. I have an excell to import that has an "alpha" character to split my P&C into 3 catag...

Dec 27, 2012

PS8 vs PSNext vs Sciforma

Forum Topic

Hello all,I have been using Project Scheduler (aka Project Scheduler Network in France because PS here is the acronym for "Parti Socialiste") since 1991.My opinion is that Project Scheduler always was far ahead of Microsoft Project; when the editor S...

Dec 28, 2012

Australia and Primavera

Forum Topic

Hi All,I am new to this forum and am in need of advice specially if we have Australians here.I have been in Australia in for quite some time now. Before that I have around 1 year of experience working as a junior scheduler in India. I am looking to b...

Dec 29, 2012