Excavate & Load

Wiki Page

Excavate Spoil Heaps and Load to Transport (m3/hr): Material0.6 m30.8 m31.0 m31.2 m3Sand/Soil20.025.630.335.7Gravel20.425.631.337.0Clay/Chalk18.523.227.833.3Boulder Clay16.921.324.430.3Note:0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity....

Feb 7, 2009

Spoil By Barge

Wiki Page

Removal / Transportation Of Spoil By Barge: The size, getting material to the facility, location and movement restrictions of the barge loading facilities are critical to production. A 2,000 m3 flat bottom barge, could easily be loaded 1.5 times per ...

Feb 7, 2009

Spoil By Conveyor

Wiki Page

Removal / Transportation Of Spoil By Conveyor: The size and location of the conveyor are critical to production and should be sized according to the most critical peaks in excavation. There are the following parameters to select... Max excavation per...

Feb 7, 2009

Elevated Watercourse

Wiki Page

Modification of an existing 6 m high elevated canal. Normal canal is 12 m in width, to allow single passing on bridge/aqueduct structures, a 5.5 m minimum width is required. Normal depth of water is 1.3 m. Some 4 number "V" shaped piers on 1,200 mm b...

Feb 7, 2009

Floating Track Slab

Wiki Page

Pre-cast concrete blocks that support standard steel tracks. They are used to reduce noise and vibration as the pre-cast track slab blocks are placed on resin pads (4 no per unit), held in place by fixed side and end restraint blocks. Side restraints...

Feb 7, 2009

Asphalt Waterproofing

Wiki Page

Asphalt coatings to prepared concrete surfaces, usually undertaken with a 3 man gang. Horizontal Surfaces = 210 m2/wk Vertical Surfaces = 85 m2/wk

Feb 7, 2009

Bituminous Waterproofing

Wiki Page

Brush applied coatings (tretol etc) to prepared concrete surfaces. A two coat application = 5.0 m2/hr A three coat application = 3.5 m2/hr Sheet materials (bituthene etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 4.0 m2/hr Vertical S...

Feb 7, 2009

Polythene Waterproofing

Wiki Page

Polythene Sheeting Sheet materials (DPC/DPM's etc) fixed to prepared concrete surfaces. Horizontal Surfaces = 20.0 m2/hr

Feb 7, 2009

Bentonite Waterproofing

Wiki Page

Sheeting to be installed and covered over immediately in order to prevent drying out, carried out with a gang of at least 3 people. Horizontal Surfaces = 25.0 m2/hr Vertical surfaces = 15.0 m3/hr

Feb 7, 2009

Epoxy Waterproofing

Wiki Page

Epoxy based material (eliminator etc), a 2 part mix. It is sprayed on and large areas can be completed in a short time. Usually carried out in two coats, good ventilation is required. A one coat application = 75 m2/hr A two coat application = 38 m2/h...

Feb 7, 2009

Concrete Pumping

Wiki Page

Large Concrete Pours, lorry pump. Simple Rule Of Thumb, concretors 0.5 - 1.0 hrs/m3 of concrete, depending on access, pour size and concrete availability. Base Slabs etc, 1,200m3 equalling 25 - 35m3/hr per pump, with 3 No pumps and 12 men for 2 shift...

Feb 7, 2009

Concrete Cycle Times

Wiki Page

Blinding Concrete Placing blinding direct from ready mix truck, rate of 4-5 m2/hr or 0.2-0.3 m3/hr. Base / Floor Slabs Concourse slab concrete pour, 36 m x 18 m, concrete volume of 1,500 m3 and 290 tonnes of reinforcement. Blind 1 day, formwork 2 day...

Feb 7, 2009

Reinforcement

Wiki Page

Mesh reinforcement - to slabs = 10.5 m2/hrMesh reinformcement - to beams/columns = 2.5 m2/hrReinforcementTask / DescriptionSlow  Ave  Fast   Units Slabs/Foundations, steelfixing, 6mm40.3 38.4 36.5  hrs/tonne Slabs/Foundations, steelfixing, 8mm28.2 26...

Feb 7, 2009

Vertical Shafts

Wiki Page

Vertical Shafts Vent shaft 10 m dia, build 1 m/day, excavate at 80 m3/day Vent shaft connecting tunnels 6m dia, build 0.75 m/day, excavate at 21 m3/day

Feb 7, 2009

Driven Piles

Wiki Page

West Piling (P.C. Shells), Rate of 100 m/day Balken Piling (Solid P.C. Pile), Rate of 120 - 135 m/day H-Piling, Rate of 200 - 500 m/day

Feb 7, 2009

Formwork Re-Use

Wiki Page

Typical rate for number of formwork uses before shutter remake. NOTE: This varies significantly depending on care taken with shutters and programme time available etc. Walls = 20 uses Slab Soffits = 10 - 15 uses Beam & Column Boxes = 30 uses

Feb 7, 2009

Waffle Flooring

Wiki Page

Rate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr). Conservative Erection Rate... 2.4 m grid, ne 3.5 m ...

Feb 7, 2009

Slip Forming

Wiki Page

Concrete - Slip Forming A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform. Rate of climb of formwork = 200 - 300 mm/hr.

Feb 7, 2009

Table Forms

Wiki Page

Concrete - Table Forms Fast method of forming walls/slabs with movable shutter. This rate is inclusive of walls and columns etc. Rate of 100 - 150 m2/day

Feb 7, 2009

Tunnel Forms

Wiki Page

Concrete - Tunnel Forms A system of forms which enables walls and slabs to be cast in the same pour. suited to buildings with large number of identically sized rooms, such as hotels or flats. Used in conjunction with high speed concrete pumps, pre-fo...

Feb 7, 2009