Search

Rule of Thumb

Wiki Page

Rule of ThumbTask / DescriptionSlow  Ave  Fast   Units Site Investigation Pre Drilling5.0 4.0 3.0  days/no Ground Excavation, Hydraulic Backhoe-  50.0 -   m3/day Bored Piling, 25-70m deep10.0 8.0 6.0  days/no Formwork Fixing-  12.0 -   m2/day Reinfor...

Jul 14, 2011

Restoration Works

Wiki Page

Restoration WorksTask / DescriptionSlow  Ave  Fast   Units Façade Cleaning, Water Jetting-  25.0 -   m2/day Façade Cleaning, Acid Etching-  9.0 -   m2/day Façade Cleaning, Grit Blasting-  12.0 -   m2/day Cladding Restoration, Brickwork-  6.5 -   m2/d...

Jul 14, 2011

Rendering

Wiki Page

RenderingTask / DescriptionSlow  Ave  Fast   Units Large Wall Areas, applied in 2 coats-  2.2 2.7  m2/hr Small Wall Areas, applied in 2 coats-  1.5 1.7  m2/hr Narrow Widths, applied in 2 coats-  1.2 1.4  m2/hr Columns and Beams, applied in 2 coats-  ...

Jul 14, 2011

Reinforcement Ratios

Wiki Page

Reinforcement RatiosTask / DescriptionSlow  Ave  Fast   Units Pile Cap, Concrete m3 x Ratio = Rebar Tonnes-  14.8 -   % ratio Base Slab, Concrete m3 x Ratio = Rebar Tonnes-  13.2 14.1  % ratio Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes-  20.6...

Jul 14, 2011

Transportation Power Supply

Wiki Page

Power SupplyTask / DescriptionSlow  Ave  Fast   Units AC Install 2 no Service transformers, 6 men-  12.0 -   days AC Install 2 no Switchgear, 7 men-  12.0 -   days AC Install Associated Trays and ladders, 3 men11.0 5.0 -   days AC Cable Terminations ...

Jul 14, 2011

Plasterboard

Wiki Page

PlasterboardTask / DescriptionSlow  Ave  Fast   Units Boarding to Plaster dabs3.6 4.0 5.5  m2/hr Boarding to Stud-work/Metal Lathes4.0 5.0 6.7  m2/hr Boarding 12mm nailed to studding-  12.5 -   m2/hr Boarding 19mm nailed to studding-  16.5 -   m2/hr ...

Jul 14, 2011

Partitioning

Wiki Page

PartitioningTask / DescriptionSlow  Ave  Fast   Units Timber Studding5.9 6.2 6.8  m/hr Metalwork System (MF) Studding1.6 2.0 2.5  m2/hr Tape, Joint Sand and Top Coat Plasterboard1.1 1.5 2.1  m2/hr Skimming to Plasterboards5.5 6.1 6.7  m2/hr 5mm Hardb...

Jul 14, 2011

Drainage, Manholes and Gulleys

Wiki Page

Manholes and GulleysTask / DescriptionSlow  Ave  Fast   Units Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm-  1.2 -   hrs/no Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm-  1.6 -   hrs/no Brickwork Manhole, 1.0 brick engineering-  0.3 -   m...

Jul 14, 2011

Kerbs & Paving

Wiki Page

Kerbs & PavingTask / DescriptionSlow  Ave  Fast   Units Concrete Slabs, laid on bedding, to slight falls2.7 -  4.2  m2/hr Concrete Slabs, laid on bedding, to steep falls2.3 -  2.7  m2/hr Concrete Slabs, laid in mortar, to slight falls1.5 -  2.3  m2/h...

Jul 15, 2011

Formwork

Wiki Page

FormworkTask / DescriptionSlow  Ave  Fast   Units Pilecaps, < 0.7m20.9 1.6 2.0  m2/hr Pilecaps, 0.7-2.5m21.6 2.0 2.3  m2/hr Pilecaps, 2.5-3.0m22.0 2.3 2.5  m2/hr Pilecaps, > 3.0m22.3 2.5 3.1  m2/hr Ground Beams, < 0.7m21.1 1.7 1.8  m2/hr Ground Beams...

Jul 15, 2011

Floor Finishes

Wiki Page

Floor FinishesTask / DescriptionSlow  Ave  Fast   Units Granolithic Flooring-  3.1 -   m2/hr Terrazzo Flooring, in-situ-  3.6 -   m2/hr Terrazzo Flooring, pre-cast-  4.6 5.1  m2/hr Mosaic Tiling, 0.045x0.045m-  1.5 2.2  m2/hr Clay, quarry Tiles, smal...

Jul 15, 2011

Fencing Works

Wiki Page

Fencing WorksTask / DescriptionSlow  Ave  Fast   Units Site Hoarding, timber posts, plywood nailed to horizontal rails1.0 1.2 -   m/hr Post Erection, Timber / Metal, dig, erect, fix3.3 4.5 -   no/hr Post Erection, Concrete, dig, erect, fix3.2 4.0 -  ...

Jul 15, 2011

Electrical System

Wiki Page

Electrical SystemTask / DescriptionSlow  Ave  Fast   Units Railway Station 1st Fix-  38.0 -   wks Railway Station 2nd Fix-  16.0 -   wks Railway Station T&C-  8.0 -   wks Cable Installation, 1 cable laid in trench and protect-  6.2 -   m/hr Cable Ins...

Jul 15, 2011

Professional Development for Project Controls

Wiki Page

Professioanl development for projects controls specailists is a tricky areas with very little on offer. Project managers seem to have a wide range of choice including PRINCE2 and APMP in the UK and PMP Certification for those in the international mar...

Jul 15, 2011

Decking

Wiki Page

DeckingTask / DescriptionSlow  Ave  Fast   Units Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover-  7.1 -   m/day

Jul 19, 2011

Excavate and Remove

Wiki Page

 Excavate and RemoveTask / DescriptionSlow  Ave  Fast   Units Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6  m3/hr Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6  m3/hr Excavate Spoil Heaps to Tr...

Oct 14, 2010

Termination of the Contract

Wiki Page

Termination of the contract For termination of a contract due to default by the Contractor, FIDIC 4th Edition provides remedies for the employer in Clause 63.1 which, save for a fairly common provision relating to the contractor’s bankruptcy, liquida...

Oct 18, 2010

Concrete Finishing

Wiki Page

Concrete FinishingTask / DescriptionSlow  Ave  Fast   Units Surface Finishing, Steel Float By Hand9.2 13.9 25.0  m2/hr Surface Finishing, Wood Float By Hand11.7 17.2 29.4  m2/hr Surface Finishing, Power Float13.9 20.8 37.0  m2/hr Surface Finishing, L...

Jul 19, 2011

Ceiling Finishes

Wiki Page

Ceiling FinishesTask / DescriptionSlow  Ave  Fast   Units Suspended Ceilings, office situations-  2.6 3.5  m2/hr Suspended Ceilings, First Fix-  0.7 -   m2/hr Suspended Ceilings, Second Fix-  1.2 -   m2/hr

Jul 19, 2011