Curtain Walling
Wiki PageCurtain Walling rateAssume 30m2 per week for general curtain wallingTask / DescriptionSlow Ave Fast Units Vertical Glazed Lights, 6m x 2.5m- 14.5 - m2/day Vertical Glazed Walls, large scale- 70.0 - m2/day Clerestory Frame/Glazing, 3m x 4m- ...
Demolition & Break Out
Wiki PageConcrete Related Works
Wiki PageFormwork
Wiki PageReinforcement
Wiki PagePlacement & Finishing
Wiki PagePre-Cast Works
Wiki PagePost Tensioning Works
Wiki PageSite Clearance
Wiki PageSite Investigation
Wiki PageSite Investigation...Task / DescriptionSlow Ave Fast Units Pre Drilling, Rercussive or Rotary, soft deposits8.0 10.0 14.0 m/hr Pre Drilling, Wash Boring, grade V/IV rock2.5 3.2 3.9 m/hr Pre Drilling, Triple Tube Sampling, grade V/IV rock0.4 0.8...
Construction Design
Wiki PageHousing Demolitions
Wiki PageDemolitionTask / DescriptionSlow Ave Fast Units Weight, Structural Steel- 2.5 - Tonnes/m3 Remove & Cart away, Ceramic Wall Tiles2.0 2.5 3.4 m2/hr Remove & Cart away, Wallpaper, 1 layer- 8.7 - m2/hr Remove & Cart away, Wallpaper, 2 layers- ...
Breaking Out & Openings
Wiki PageCutting Back
Wiki PageCutting Back Concrete Cutting Piles For Pile Caps, Using Breaker & Air Tools Providing A Rough Finish (hrs/pile)Pile Diameter-->0.35m0.5m0.6m0.79m0.94m1.1m2.2m0 - 100mm high0.320.440.630.931.381.74 8.10100-200mm high0.390.560.811.221.832.16 8.58200-3...
Cutting Chases
Wiki PageCutting ChasesTask / DescriptionSlow Ave Fast Units Concrete, cutting by hand, < 25mm wide1.5 2.1 3.1 m/hr Concrete, cutting by hand, 25-50mm wide1.2 1.6 2.5 m/hr Concrete, cutting by hand, 50-75mm wide1.0 1.4 2.1 m/hr Concrete, cutting by han...
Cutting Switchboxes
Wiki PageCutting SwitchboxesTask / DescriptionSlow Ave Fast Units Cutting in Concrete, small box7.1 9.5 12.5 no/hr Cutting in Concrete, large box3.6 4.5 5.6 no/hr Cutting in Brickwork, small box6.6 9.5 12.5 no/hr Cutting in Brickwork, large box4.2 5.3 ...
Spread & Leveling
Wiki PageSpread and LevelTask / DescriptionSlow Ave Fast Units Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile13.9 20.4 25.0 m3/hr Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile7.6 9.5 12.6 m3/hr Crawler Shovel, ...