FORENSIC / DELAY SCHEDULE ANALYSIS – SUMMARY GRAPHIC REPORT IN 1 PAGE
|
 |
Summary Graphics: whether it be a Time Impacted Analysis / Window Analysis or an As-Built But-For / Collapsed As-Built Analysis after finishing such an analysis using Primavera P6 or even MS Project, we need to make a summary graphic report for the high-level managers so that they can appreciate the big picture. Here's how...
|
|
|
A MESSAGE FROM THE PLANNING PLANET FOUNDER... CALLING ALL PMPers...
|
 |
UPDATE: thanks again you all for your thoughts and messages about the PMP mapping to the Guild of Project Controls Certifications.
We are now part way to building that core of PMP holders so thanks for your support and encouraging words.
Regards... [email protected]
If you have a PMP and a SOLID EXPERIENCE profile contact me to get on the list to claim your Planning & Scheduling Professional Certification (PSPC) AND Cost Management Professional Certification (CMPC) in regognition of what you learned in your PMP.
|
|
|
HOW TO PERFORM COLLAPSED AS BUILT IN PRIMAVERA P6
|
 |
We had so much interest in this we decided to put it in here again; we hope you continue to find it to be of use.
An Collapsed As-Built / As-Built But-For Schedule Delay Analysis is a retrospective analysis technique that determines the earliest date that the required project completion activity could have been achieved but-for the owner-caused delays that occurred during the project. Read more...
|
|
|
CASE STUDY: INCREASING SCALABILITY & REDUCING PROJECT COST AT AECOM
|
 |
Efficiently leveraging data can challenge any project. Many companies, particularly those working on large-scale projects, have challenges managing large volumes of data in spreadsheets. The resulting reporting lag and lack of standardization can make project decisions far more difficult than they need be. Download this case study to learn how AECOM, a global engineering and construction company, is utilizing ARES PRISM project lifecycle management software to massively reduce project cost, gain complete insight into their data, and improve repeatability of analysis.
Download the Study...
|
|
|
"PROVEN PRACTITIONER" A PLANNING PLANET PRODUCT
|
 |
Do you seek PROMOTION or do you want to better UNDERSTAND YOUR Stengths and SKILLS (in private) or do you seek that NEW ROLE?
Proven Practitioner provides ALL THE TOOLS YOU NEED
Go to Premium and sign up!
Have the first month free at this low INTRODUCTORY PRICE!
|
|
|
PRIMAVERAREADER
|
 |
|
How Much of Incomplete and Incorrect Data Passes Through The Hands of Schedulers and Project Controls
PrimaveraReader™ allows the user to always know how the project team is functioning, whats the status of project activities and which critical problems require immediate attention.
|
 |
|
Clear, understandable, well formatted and customizable P6 information
The solution works with files exported from Oracle® Primavera P6 without connecting to the main database making it the perfect P6 companion tool for quickly checking Project, Activities Status, creating Dynamic Reports and more.
Download your Free Trial
|
|
|
HOW TO CALCULATE EARNED SCHEDULE
|
 |
In this training video they will show you how you can calculate the “Earned Schedule”. To measure Earned Schedule, we need to determine “when” the work was supposed to be earned. In other words, at what point in time was the current Earned Value (EV) should have been occurred?
Read more...
|
|
|
CLEOPATRA ROADSHOW NORTH AMERICA and AUSTRALIA
|
 |
Drive Project Success with Disruptive Innovation
In the era of digital disruption, delivering project success requires putting in place the right project cost management tool with intensive integration capabilities.
‘Digital technologies, when applied comprehensively and efficiently, can reduce overall project costs by as much as 45 percent.' as a recent McKinsey analysis suggests.
|
|
However, 64 percent of technical projects still face cost overruns. Despite many challenges, companies applying integrated project controls complete their projects within time and budget and drive project success.Cleopatra Enterprise LLC will meet with various companies through the USA & Canada and Australia, showcase our state-of-the-art software Cleopatra, and discuss:
- How to drive project success in today’s challenging environment
- The value of using a project controls software that integrates the disciplines cost estimating, scheduling, cost management and benchmarking
- Best practices in project controls, which bring continuous improvement with Cleopatra Enterprise
USA & Canada
Date: 29 October - 9 November 2018
Location: Houston, Calgary, and Edmonton - Schedule a meeting in the USA & Canada
Australia
Date: 19 – 23 November 2018
Location: Melbourne, Sydney, and Perth - Schedule a meeting in Australia
|
|
|
HOW TO MANAGE UNKNOWNS IN YOUR CONSTRUCTION PROJECTS
|
 |
Learning how to manage unknowns in your project sounds very tricky and complicated but it isn’t.
Every construction project, from design to physical installation will go through numerous processes and challenging situations that can derail the actual purpose of the project.
Read more...
|
|
|
WHAT IS A WORK PACKAGE IN PROJECT MANAGEMENT?
|
 |
You might have seen the term come up a lot, especially when talking about a Work Breakdown Structure (WBS), and wondered to yourself what is a work package anyway?
Well, a work package is a collection of similar tasks which are bundled together to create a kind of mini-project within a project. What defines a work package is the inter-relatedness of the tasks involved, as they must have elements which connect them. Read Clarizen's Blog...
|
|
|
HOW TO PLACATE DISSATISFIED STAKEHOLDERS
|
 |
As we have looked at previously, project stakeholders come in all shapes and sizes, can be internal or external and have varying levels of impact on your project’s progress. One thing that is for certain though, is that if your project starts to hit roadblocks such as persistent delays or cost overruns, your project stakeholders will start to get concerned and ask questions about what’s going on. Read Clarizen's Blog... |
|
|
COMPETENCY MEASUREMENT REPORTS
|
 |
We are now offering Project Controls Competency Measurements for our members!
From this report, you will receive a summary, similar to the one presented above, showing your teams, company’s or projects "Competency Performance Index" across the full Project Controls capability arena. If you are interested in transforming Project Controls capability and team measurement, and would like to find out more, click here.
|
|
|
UPCOMING MEETINGS AND EVENTS
|
 |
Our Project Controls Gatherings are a great opportunity for our members to discuss industry issues, share ideas and form new connections. Here is a list of our upcoming gatherings...
These meetings may just form the beginning of lasting professional relationships. Don’t miss out! Follow the links above to sign up.
What should I do if I can't see a meeting near me?
If you don’t see an event near you listed above, why not create your own? Just email [email protected] to get started.
To make sure these events can be as successful as possible, please forward this to your friends and colleagues so they can also get involved.
|
|
|
CONSTRUCTION CPM CONFERENCE RETURNS IN 2019
|
 |
San Diego, California - JANUARY 20 – 23, 2019
For 2019 the Construction CPM Conference returns to San Diego
We have booked six meeting rooms over three full days.
Two keynotes – Seventy-Seven breakouts – Five networking events – One conference
Our Best Rates for Speakers & Exhibitors is open to all – REGISTER NOW
|
|
|
PROJECT CONTROLS ROLE EXPECTATIONS
|
 |
|
Have you taken a look at the Guild of Project Controls' Role Descriptors yet?
This is the perfect tool for those who want to find out the baseline knowledge required for their role and level of seniority - think of it as a job descriptor for all roles and levels of competence. Give it a try here, find out more here.
|
|
|
PROJECT CONTROLS TOOLBOX
|
 |
Contact [email protected] if you would like to learn about getting our Project Controls Toolbox for...
- yourself,
- your team,
- your project, or
- your company
|
|
|
RATES, NORMS & DURATIONS
|
 |
What is needed to come up with a production rate?
A duration of time, the manhours involved, and an amount of work produced
This section of Planning Planet is here to document this.
What information do you have that you can share?
|
|
|
ALTERNATIVE TO PRIMAVERA AND ASTA?
|
 |
A superior alternative to the "most popular" software for us as planners?
Spider Project (SP) is a functional and powerful professional project management software.
Today it is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios. Check it out here...
|
|
|
PLANNING PLANET PREMIUM is the title we are giving a number of member only products we are developing to help you - our community of Project Controls Practitioners.
For £7.50 a month subscribers have access to online self-assessments where they can measure and visualise their skill levels. If subscribers wish to improve and fill knowledge gaps this subscription supplies tools that will help them improve and re-assess whenever they want to prove the improvement they have made.
The subscription supplies a certificate proving you KNOW the tools and one proving you can APPLY the tools.
Get involved here!
|
|
JACOBS JOBS
|
 |
|
Opportunities await you. We are working on some of the most exciting, iconic projects around the world.
Jacobs has recently won a major contract, known as the Programme Delivery Partner (PDP) – for the provision of project management, project controls and integrated logistics support - with the Ministry of Defence's (MOD's) Defence Equipment and Support (DE&S) Agency, based in Bristol. DE&S is seeking our support at their offices across the UK and we are, therefore, keen to identify people who are interested in working for Jacobs, and being involved in PDP, across the UK.
We invite YOU to bring your best self to work with us and progress your career on either this exciting new project or one of the other exciting projects and programmes Jacobs is supporting across the UK. Join our team and say “Hello” to a whole new future.
|
|
|
|
|
ARE YOU FOLLOWING US ON SOCIAL MEDIA?
|
|
|
|
THE GUILD OF PROJECT CONTROLS COMPENDIUM AND REFERENCE
|
 |
The Compendium and Reference (CaR) is a document which forms The Guild Standards.
We have where possible offered advice as to previously written material which is in the public domain and proven to be of such quality that it can be used as a reliable reference of "best tested and proven practice".
The CaR is a living document being continually improved, supplemented and updated by the Guild community to reflect improvements to practices, opinions and methods in our chosen profession. The Guild is ready to receive suggestions at any time for updates to the CaR Standards.
Take a look here.
|
|
 |
|
WOULD YOU LIKE TO ADVERTISE ON PLANNING PLANET?
We want to give more of our members the opportunity to advertise on our site. There are many reasons why this would be beneficial to anyone wanting to advertise their goods or services. We are offering two levels of interaction with our community, PP SILVER ADVERTISER and PP GOLD ADVERTISER.
Click here to get started!
|
 |
|
WOULD YOU LIKE TO BECOME A GUILD OF PROJECT CONTROLS CORPORATE MEMBER?
This is our effort to help YOU - the employers of our community. Becoming a Corporate Member will allow you to:
- Better understand your ENTIRE Project Controls environment in terms of workforce
- Assess the competence of all your staff to fully understand their strengths and weaknesses
- Use the experience of our huge community in order to run your team much more efficiently
- Raise the morale of your staff as they will have much more confidence in their ability
- Recruit the best possible personnel
- Transform your profits!
All of the above is carried out with YOU in control!
With a Corporate Membership, you will have access to many of our services including Role Descriptors, Self Assessment, Competency Review with possible comparison with other organisations and Compendium Desk Reference and so many more.
Interested? Click here.
|
|
GUILD ASSESSMENT CENTRE
|
 |
Have you tried the Guild of Project Controls' Assessment Centre?
From this tool you will be able to ascertain your strengths and weaknesses against the many years of research that the Guild has ascertained are the Standards required for your role.
Further, for the first time you will know how you stack up in terms of skills in the Project Controls industry whatever your role.
Give it a try here!
|
|
|
PROJECT CONTROLS EVENTS
|
 |
We will be attending Project Controls events at these locations this year, if anyone wishes to attend or sponsor or speak or simply to come help us please do email [email protected] and he will put you in touch with the relevant people.
We look forward to meeting you throughout the year.
- PC Expo London – Nov 13-14
- Melbourne, AU – Nov 28
- Kuwait city, Kuwait – Nov 30
- Rio, Brazil – Dec 06
- Porto, Portugal – Mar 19
|
|
 |
|
WOULD YOU LIKE TO BECOME A GUILD REGISTERED CONSULTING PARTNER?
This is our effort to help YOU and our community. It is about having a product in your portfolio that any organisation with a Project Controls environment will be interested in. This is a GLOBAL opportunity:
- You represent GPC to the client - YOU are our REGISTERED PARTNER
- There will have to be screening by us but essentially if you are an established consultancy OR have considerable skills and knowledge CALL US ON THE NUMBERS BELOW
- Your client is yours - we recognise this and will protect your relationship if required
- We have fixed costs - your margin and you total deliverables are up to you!
The Guild of Project Controls offers a solution - which evaluates a Project Controls environment by Assessing and grading the competency of individuals - a ‘stake in the ground’ - a report to document the actual competence of my team.
If you are interested in becoming a Guild Registered Consulting Partner, click here.
|
|
ARE YOU TAKING FULL ADVANTAGE OF PLANNING PLANET?
|
| |
 |
MEMBERS
See who you know from within our 150,000+ membership pool!
|
 |
GUILD
Take a look at the worlds first and only competence based credentials supported by a career path, role descriptors, self-assessment tools and online compendium desk reference of best tested and proven tools and techniques for project controls practitioners.
|
 |
BLOG
Join other members who share their thoughts and ideas in the form of blog posts.
|
 |
FORUM
100,000+ questions and answers to the topics we struggle with (mostly software!) on a day to day basis.
|
 |
WIKI
A knowledge-base that can be contributed to or utilized by anyone with skills and/or interest in planning, scheduling or project controls. No Wiki page or article is owned by its creator or any other editor, and its content relies upon collaboration and teamwork. How can you contribute?
|
 |
BUILD TIMES
What is needed to come up with a production rate? A duration of time, the manhours involved, and an amount of work produced? Take a look and get involved.
|
 |
JOBS
This has been dusty and quiet place for some time now. We have been liaising with recruiters, headhunters and talent managers plus a ream of corporate leaders and very soon we will have the largest live repository of project controls jobs in the world. Check back soon.
|
 |
ADVERTISERS
Check out our Silver and Gold partners and see if you'd like to be included there also.
|
|
 |
|
ARE YOU INTERESTED IN BECOMING A GUILD ENDORSED TRAINING PROVIDER?
Are you an experienced Practitioner in Project Controls? Or are you already involved in Project Delivery Training or Project Management software sales, support, and installation? We seek a cohesive delivery team for our training - email us at [email protected] to find out more.
|
 |
If you got this far please email us to tell us - we will include your profile in the next newsletter as our "Validated Super-Readers" :) |
|
|
Thank you for reading our short message.
If you'd like to help the small but enthusiastic team of people helping with this newsletter please do get in touch with us via [email protected] We know we have a long way to go to make this informative and an anticipated bi-weekly "read" so do get in touch and get involved.
Regards...
The Planning Planet Team
|