I meant that critical activities on distance diagram. Now I understand that I can display/switch off all CPM terms.
On display tab I found the icons to display Links, Total float, Free float, Constraints, Critical path, Baseline tasks, Progress info, Calendars and more, here there are more items than I need :)
the critical path and the floats are calculated results from the reschedule. The definition is very similar to the CPM float definition. To can switch on/of the display of the float and critical path in the time-distance view: Please select the time-distance cell first, then use the tab "Display" and check the flags "Critical Path", "Total float" or "Free float".
Regarding the critical distance: What do you understand as critical distance?
Member for
13 years 4 monthsDear Thorsten,I meant that
Dear Thorsten,
I meant that critical activities on distance diagram. Now I understand that I can display/switch off all CPM terms.
On display tab I found the icons to display Links, Total float, Free float, Constraints, Critical path, Baseline tasks, Progress info, Calendars and more, here there are more items than I need :)
Thank you for your kind help!
Member for
14 years 4 monthsHi Serkan,the critical path
Hi Serkan,
the critical path and the floats are calculated results from the reschedule. The definition is very similar to the CPM float definition. To can switch on/of the display of the float and critical path in the time-distance view: Please select the time-distance cell first, then use the tab "Display" and check the flags "Critical Path", "Total float" or "Free float".
Regarding the critical distance: What do you understand as critical distance?
Good Luck
Thorsten