How can i hide or show the critical distance and time floats in Tilos?

Member for

13 years 4 months

Dear Thorsten,

I meant that critical activities on distance diagram. Now I understand that I can display/switch off all CPM terms.

On display tab I found the icons to display Links, Total float, Free float, Constraints, Critical path, Baseline tasks, Progress info, Calendars and more, here there are more items than I need :)

Thank you for your kind help!

Member for

14 years 4 months

Hi Serkan,

the critical path and the floats are calculated results from the reschedule. The definition is very similar to the CPM float definition. To can switch on/of the display of the float and critical path in the time-distance view: Please select the time-distance cell first, then use the tab "Display" and check the flags "Critical Path", "Total float" or "Free float".

Regarding the critical distance: What do you understand as critical distance?

 

Good Luck

Thorsten

 

TILOS Website: http://www.tilos.org