If the steel structure does not have to be lined and levelled before any concrete casing can be applied then:
You can use wrinkly steel formwork for the floor slabs and they can be placed as the steel goes up and can be concreted with backprops as soon as they are three floors up.
The columns can be cased as soon as the floor slab is 3 days cured.
Member for
19 years 10 monthsHi Ashik If the steel
Hi Ashik
If the steel structure does not have to be lined and levelled before any concrete casing can be applied then:
You can use wrinkly steel formwork for the floor slabs and they can be placed as the steel goes up and can be concreted with backprops as soon as they are three floors up.
The columns can be cased as soon as the floor slab is 3 days cured.
Best regards
Mike Testro
Member for
12 years 7 months2nd option is good for
2nd option is good for maintaning cash flow.
hindrance can be avoided for structural work by proper zone segeration, keeping safety and quality norms in place.