Construction Methodology for Structural Steel with Deck Slab Concreting

Member for

19 years 10 months

Hi Ashik

If the steel structure does not have to be lined and levelled before any concrete casing can be applied then:

You can use wrinkly steel formwork for the floor slabs and they can be placed as the steel goes up and can be concreted with backprops as soon as they are three floors up.

The columns can be cased as soon as the floor slab is 3 days cured.

Best regards

Mike Testro

Member for

12 years 7 months

2nd option is good for maintaning cash flow.

hindrance can be avoided for structural work by proper zone segeration, keeping safety and quality norms in place.