Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2018-06-04 14:04 Permalink what columns are you what columns are you displaying ? Member for 9 years 2 months Member for 9 years 2 months Submitted by zahidshaikh on Mon, 2018-06-04 11:41 Permalink After maintain baseline did After maintain baseline did you do assign baseline? Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Sun, 2012-10-28 11:42 Permalink John, A common issue, which John, A common issue, which Paul Harris has addressed very well is this presentation: http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf Cheers, G Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Sun, 2012-10-28 11:34 Permalink John,Open March Program and John, Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires. Hope this will help. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2018-06-04 14:04 Permalink what columns are you what columns are you displaying ?
Member for 9 years 2 months Member for 9 years 2 months Submitted by zahidshaikh on Mon, 2018-06-04 11:41 Permalink After maintain baseline did After maintain baseline did you do assign baseline?
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Sun, 2012-10-28 11:42 Permalink John, A common issue, which John, A common issue, which Paul Harris has addressed very well is this presentation: http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf Cheers, G
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Sun, 2012-10-28 11:34 Permalink John,Open March Program and John, Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires. Hope this will help.
Member for
16 years 3 monthswhat columns are you
what columns are you displaying ?
Member for
9 years 2 monthsAfter maintain baseline did
After maintain baseline did you do assign baseline?
Member for
16 years 7 monthsJohn, A common issue, which
John,
A common issue, which Paul Harris has addressed very well is this presentation:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G
Member for
15 years 11 monthsJohn,Open March Program and
John,
Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.
Hope this will help.