Can't get P6 to assign Baseline dates

Member for

16 years 3 months

what columns are you displaying ?

Member for

9 years 2 months

After maintain baseline did you do assign baseline?

Member for

15 years 11 months

John,

Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.

Hope this will help.