How to Change Cutt off dates (weekly base)

Member for

16 years 3 months

admin 

admin preferences

General tab

Starting Dau of Week Chanhe this to Saturday

this will end the week on Friday

Member for

6 years 4 months

Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.