Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-06-11 13:27 Permalink admin admin admin admin preferences General tab Starting Dau of Week Chanhe this to Saturday this will end the week on Friday Member for 6 years 4 months Member for 6 years 5 months Submitted by mohamed azarudeen on Mon, 2019-06-10 14:13 Permalink Select Enterprise-> Calendar Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there. Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Thu, 2010-09-16 11:28 Permalink How to Change Cutt off dates (weekly base) hi, We can set it at Admin preferences->General->starting day of week. Best Regards. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-06-11 13:27 Permalink admin admin admin admin preferences General tab Starting Dau of Week Chanhe this to Saturday this will end the week on Friday
Member for 6 years 4 months Member for 6 years 5 months Submitted by mohamed azarudeen on Mon, 2019-06-10 14:13 Permalink Select Enterprise-> Calendar Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.
Member for 19 years 11 months Member for 19 years 11 months Submitted by niles luo on Thu, 2010-09-16 11:28 Permalink How to Change Cutt off dates (weekly base) hi, We can set it at Admin preferences->General->starting day of week. Best Regards.
Member for
16 years 3 monthsadmin admin
admin
admin preferences
General tab
Starting Dau of Week Chanhe this to Saturday
this will end the week on Friday
Member for
6 years 4 monthsSelect Enterprise-> Calendar
Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.
Member for
19 years 11 monthsHow to Change Cutt off dates (weekly base)
hi,
We can set it at Admin preferences->General->starting day of week.
Best Regards.