P6 Activity Order and Sort Problem by "Start Date"

Member for

16 years 3 months

go to group and sort and group it as you want then on the right select sort then add the order there

Member for

9 years 4 months

I am having a similar issue.  I created my schedule and then later needed to add a new activity.  I've left room in the Activity ID's for the new activity to be in the desired corresponding order. The duration, start time and stop time are all identical to Activities A and B but no matter how I sort my activities the new activity is always 3rd in the sequence behind A and B.

Member for

15 years 4 months

Cheers for this one Richard! Worked a treat, keep up the good work. 

Many thanks,

Vas

Member for

22 years 7 months

Greg,

 

A very old posting, but in the Group and Sort Field, you can apply multiple Sortings, to further filter the sorting criteria. In this scenario, firstly sort by Start Date ascending, and then a secondary sort by Finish Date ascending. This way whenever you have a Start Milestone and a Task starting on the same date, by default, the activity will finish later than the Milestone and appear below it

 

Regards

 

Richard Rowberry

Member for

19 years

Greg,

By default Primavera used sorting field by unique field sequence number (which data ever created first). It means that if you created the task before the milestone then task will always above the milestone if both are sorted on the same field identifier.



Ex: Act1 = Task and Act2 = Milestone.

If Act2->FS-> Act1 then it will sort as task then milestone because milestone has zero duration and it will start on the same time (sorting field start).



You can create any sort field to solve this but I recommend using Activity ID and aligned the Activity ID to sort correctly. (Group & Sort: Start then Activity ID)

Member for

15 years 7 months

Gary,



Try sorting out by Start date first and then Activity type...it should put the milestone above the activities even if starting the same day.



Or



Create a sort ’UDF’ auto fill it and then sort it the way you want to. It is not difficult even for 4000 activity schedules.



Regards




Member for

16 years 7 months

I’m no P6 expert either, but could you not just sort by start date and then by activity type?

Member for

19 years 10 months

Hi Greg



Welcome to Planning Planet



Just a guess because I don’t use P6 - is the Link from the milestone SS or SF?



Best regards



Mike Testro