I am having a similar issue. I created my schedule and then later needed to add a new activity. I've left room in the Activity ID's for the new activity to be in the desired corresponding order. The duration, start time and stop time are all identical to Activities A and B but no matter how I sort my activities the new activity is always 3rd in the sequence behind A and B.
Member for
15 years 4 months
Member for15 years4 months
Submitted by Vasilios Sarras on Fri, 2013-12-13 10:25
A very old posting, but in the Group and Sort Field, you can apply multiple Sortings, to further filter the sorting criteria. In this scenario, firstly sort by Start Date ascending, and then a secondary sort by Finish Date ascending. This way whenever you have a Start Milestone and a Task starting on the same date, by default, the activity will finish later than the Milestone and appear below it
Regards
Richard Rowberry
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Tue, 2010-08-24 01:44
By default Primavera used sorting field by unique field sequence number (which data ever created first). It means that if you created the task before the milestone then task will always above the milestone if both are sorted on the same field identifier.
Ex: Act1 = Task and Act2 = Milestone.
If Act2->FS-> Act1 then it will sort as task then milestone because milestone has zero duration and it will start on the same time (sorting field start).
You can create any sort field to solve this but I recommend using Activity ID and aligned the Activity ID to sort correctly. (Group & Sort: Start then Activity ID)
Member for
15 years 7 months
Member for15 years7 months
Submitted by Rashid Iqbal on Mon, 2010-08-23 17:16
Member for
16 years 3 monthsgo to group and sort and
go to group and sort and group it as you want then on the right select sort then add the order there
Member for
9 years 4 monthsI am having a similar issue.
I am having a similar issue. I created my schedule and then later needed to add a new activity. I've left room in the Activity ID's for the new activity to be in the desired corresponding order. The duration, start time and stop time are all identical to Activities A and B but no matter how I sort my activities the new activity is always 3rd in the sequence behind A and B.
Member for
15 years 4 monthsCheers for this one Richard!
Cheers for this one Richard! Worked a treat, keep up the good work.
Many thanks,
Vas
Member for
22 years 7 monthsGreg, A very old posting, but
Greg,
A very old posting, but in the Group and Sort Field, you can apply multiple Sortings, to further filter the sorting criteria. In this scenario, firstly sort by Start Date ascending, and then a secondary sort by Finish Date ascending. This way whenever you have a Start Milestone and a Task starting on the same date, by default, the activity will finish later than the Milestone and appear below it
Regards
Richard Rowberry
Member for
19 yearsRE: P6 Activity Order and Sort Problem by
Greg,
By default Primavera used sorting field by unique field sequence number (which data ever created first). It means that if you created the task before the milestone then task will always above the milestone if both are sorted on the same field identifier.
Ex: Act1 = Task and Act2 = Milestone.
If Act2->FS-> Act1 then it will sort as task then milestone because milestone has zero duration and it will start on the same time (sorting field start).
You can create any sort field to solve this but I recommend using Activity ID and aligned the Activity ID to sort correctly. (Group & Sort: Start then Activity ID)
Member for
15 years 7 monthsRE: P6 Activity Order and Sort Problem by
Gary,
Try sorting out by Start date first and then Activity type...it should put the milestone above the activities even if starting the same day.
Or
Create a sort UDF auto fill it and then sort it the way you want to. It is not difficult even for 4000 activity schedules.
Regards
Member for
21 years 8 monthsRE: P6 Activity Order and Sort Problem by
What about sorting by start date and then by WBS code?
Member for
16 years 7 monthsRE: P6 Activity Order and Sort Problem by
Im no P6 expert either, but could you not just sort by start date and then by activity type?
Member for
19 years 10 monthsRE: P6 Activity Order and Sort Problem by
Hi Greg
Welcome to Planning Planet
Just a guess because I dont use P6 - is the Link from the milestone SS or SF?
Best regards
Mike Testro