HOW CAN I MAKE CALENDER

Member for

19 years 8 months

also i wark in net work ani i trayed many time to change hour per day to 24

but i can not

it is fixed on 8 hours per day

could you tell me what can i do

Member for

19 years 8 months

if i want to change only one project what i will do

Member for

20 years

But remember ... doing it ... u will chenge all projects!!!

Member for

19 years 11 months

to change "hours per time period" you need to be logged in as admin and go to [admin]>[admin preferences]> tab [time periods] then you can do what ever you want.



this is all! (see more ad nr: #11)

Member for

19 years 8 months

COOULD YOU TELL ME HOW CAN I WILL CONTACT WITH ADMIN TO CHANGE DURATION

I WANT TO SEE

24= 1 DAY

BUT IN MY PROJECT

24 HOURS = 3 DAYS

THAT MEAN 8 DAYS PER DAY ONLY ( SHIFT = 8 HOURS )

AND I WANT SHIFT = 24 HOURS

I CHANGED CALENDER TO 24* 7

BUT THE SAME PROPLEM FACED ME

ALSO I DO DEFULT FOR MY CALENDER 24*7

BUT I FIND

24= 3 DAYS

THANK YOU

Member for

19 years 11 months

the problem can be solved by chance settings in user preferences.



Actions> go to [edit]>[user preferences] tab[time units] then under [Durations format] and set unit of time to [Hour].



you will see now that od of 24 hrs = one day.



tis problem is caused by your settings in [units per time period] you can change it in admin pref’s (primavera use this as a conversion rule for calculate differend units back to hr’s. every project is calculated to hrs in the background of the database)



hope this is usefull.

greetz vito

Member for

20 years 1 month

Interesting to hear that someone else has the same problem with the durations when changing calendars. In my view the calendar selected should override all other time settings. Is this a fault that should be reported to Primavera, if not done already?

Member for

19 years 8 months

DEAR /A LL

I already done all this steps but problem still .

I want to tell you problem in details

First I create new calendar 24*7 days and done new tasks with new calendar

Example :-

First task 24 hours ( that mean this will stay 1 day )

After that when I go to user preference to change hour to day

24 hours appear = 3 days ( that mean 1 days =8 hours )

This is problem

I create calendar 24 hours per day but system use default calendar 8 hours per day

This is problem

In another side I go to defult to set new calendar but problem still

24 hours = 3 days

And I want

24 hours = 1 day





Another problem original duration

When I create some steps and I want to see summation of all duration of this tasks in main original duration

But I found number in original duration is not correct

Could you solve me this problem

Thank you












Member for

20 years

You also need to be aware of the global ’Time Period’ settings under ’Admin Preferences’. The duration entered (in days) is worked out (in hours) using the Admin Preferences and converted back to a duration using the activity calendar.



For example:

Global Time periods are set to 24h/d, 7d/wk etc.

No resources, activities are task dependent.



EXAMPLE 1 - 8hrs x 5d Calendar

Duration entered=5days=24*5=120hrs. Based on 8x5 the duration will be 15days, excluding weekends (120/8)

Start=20/2/06

Finish=10/3/06



EXAMPLE 2 - 10hrs x 7d Calendar

Duration entered=5days=24*5=120hrs. Based on 10x7 the duration will be 12days, including weekends (120/10)

Start=20/2/06

Finish=3/3/06



Hope this helps.

Cheers

Julie

Member for

20 years

Create a resource;



Create a resource shift with 1 shift 24 hrs;



Assign this resource to activities;



Actvity Type = Resource Dependent.



Think thats it, hope it works.



Regards.

Member for

20 years 1 month

I’ve found a similar problem. I have a calendar which is 10 hrs x 7 days and cannot get the durations to calculate properly (I get strange start and finish hours, with activities spread over 3.5 instead of 2 days, for example. I’ve tried changing the settings under User Preferences, but this doesn’t really work as it affects activities on other calendars, and of course it affects other projects.



Do I have to change other calendars elsewhere, such as WBS or project? None of which makes sense - surely if I specify a calendar to an activity it should override any defaults. It works fine when I use other calendars, such as for railway possessions which are often strange hours overnight at weekends!!



Looking forward to hearing from anyone!



Emma

Member for

19 years 8 months

dear / Julie Scully

could you please tell me steps in detalies

i am new in primavera enterprice

and this case is very comflect

please tell me frist do that , second do that , third do that

also please tell me criteria in global change

thank you

Member for

20 years

Tamer



You will need to assign this new 24x7 calendar as the default calendar for the project for new activities to automatically have it assigned. You will also need to change the calendar assigned to each of your existing activities; either by adding the calendar column to your view and filling down, or doing a global change.



Cheers

Julie

Member for

19 years 8 months

i can not find any solution for my question

please tell me steps

thank you