Milestone Costs - P3 to P3e Conversion

Member for

22 years 3 months

In activity view go to Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options. On the data tab, select to display Cost and then tick the Total check box to display a curve for all costs.



Regards



KB