Oracle Primavera - PM6 Member for 20 years 5 months Member for 20 years 5 months Submitted by Andy Quinn on Fri, 2005-08-05 10:11 Permalink RE: Milestone Costs - P3 to P3e Conversion Thanks Kevin Looks like I was looking at resource profile and not activity profile. Andy Member for 22 years 3 months Member for 22 years 3 months Submitted by Kevin Button on Thu, 2005-08-04 21:36 Permalink RE: Milestone Costs - P3 to P3e Conversion In activity view go to Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options. On the data tab, select to display Cost and then tick the Total check box to display a curve for all costs. Regards KB Log in or register to post comments
Member for 20 years 5 months Member for 20 years 5 months Submitted by Andy Quinn on Fri, 2005-08-05 10:11 Permalink RE: Milestone Costs - P3 to P3e Conversion Thanks Kevin Looks like I was looking at resource profile and not activity profile. Andy
Member for 22 years 3 months Member for 22 years 3 months Submitted by Kevin Button on Thu, 2005-08-04 21:36 Permalink RE: Milestone Costs - P3 to P3e Conversion In activity view go to Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options. On the data tab, select to display Cost and then tick the Total check box to display a curve for all costs. Regards KB
Member for
20 years 5 monthsRE: Milestone Costs - P3 to P3e Conversion
Thanks Kevin
Looks like I was looking at resource profile and not activity profile.
Andy
Member for
22 years 3 monthsRE: Milestone Costs - P3 to P3e Conversion
In activity view go to Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options. On the data tab, select to display Cost and then tick the Total check box to display a curve for all costs.
Regards
KB