Primavera Contractor S Curves

Member for

17 years 9 months

Dear

You can get the S - Curve for duration. Do one thing put One Resourse (  say  - Parameter ) to all activity with 1/d .

then go to Report option and extract report from resourse & roll assignment.

you will get S -Curve.