Primavera Project Planner - P3 Member for 17 years 9 months Member for 17 years 9 months Submitted by Mohammad Mojah… on Thu, 2011-11-17 13:55 Permalink Dear You can get the S - Dear You can get the S - Curve for duration. Do one thing put One Resourse ( say - Parameter ) to all activity with 1/d . then go to Report option and extract report from resourse & roll assignment. you will get S -Curve. Log in or register to post comments
Member for 17 years 9 months Member for 17 years 9 months Submitted by Mohammad Mojah… on Thu, 2011-11-17 13:55 Permalink Dear You can get the S - Dear You can get the S - Curve for duration. Do one thing put One Resourse ( say - Parameter ) to all activity with 1/d . then go to Report option and extract report from resourse & roll assignment. you will get S -Curve.
Member for
17 years 9 monthsDear You can get the S -
Dear
You can get the S - Curve for duration. Do one thing put One Resourse ( say - Parameter ) to all activity with 1/d .
then go to Report option and extract report from resourse & roll assignment.
you will get S -Curve.