Is there resource calander in P3????

Member for

21 years 8 months

Alexandre,

Maybe you can help me remember how P3 and P6 deal with the following simple scenario that combines independent resources with meeting resources.

Resources A, B and C can work independently of each other but only when D is available, all within Activity 1 calendar.

There is only one of each resource A, B, C and D and all work on the same shift, from 8 to 5.

 

Sunday

Monday

Tuesday

Wednesday

Thursday

Friday

Saturday

Resource A

 

available

available

available

available

 

 

Resource B

 

 

available

available

available

available

 

Resource C

 

available

available

 

available

available

 

Resource D

available

 

available

available

 

available

available

Activity 1

 

available

available

available

 

available

 

Activity 1 will be scheduled to work on Tuesday, Wednesday and Friday, three days a week, but not all resources will be working on the same day.

The following is how I model it now.

Meet and Indep Resources

How P3 and P6 handle this 2 activities, 4 resources one shift job?

Best Regards,

Rafael

Member for

22 years 9 months

Hello,

it's not 100% true: in P3 each and every resource gets automatically its own calendar; create a new resource and then go to Data, Calendars, Resources and you will see this new resource specific calendar;

in the Data, Resources dialog, the "Base" column displays the "Base" calendar P3 is using as a template for this specific resource's calendar

In P6 on the other hand, resources do not get a calendar when you create them; you will have to create resource calendars and assign them to resources if needed.

Alexandre

Member for

15 years

many many thanks 

Member for

21 years 8 months

Yes you can use resource calendars in P3, somewhat limited though.

From: http://download.oracle.com/docs/cd/E20557_01/documentation/P3/P330ref.pdf

"Use resource calendars to accurately reflect the work schedules of
your resources: personnel vacations and holidays, equipment
delivery or lease dates, expected arrival dates, and so forth. P3 only
uses resource calendars to schedule independent and meeting
activities. When you define calendars for resources and assign
those resources to activities, be sure the resources are driving and
the activity type is independent or meeting."

Member for

16 years 11 months

Hi  jiahd aldaoud

Default resource calendar is unavailable in P3,you can create a calendar in which resource availability is identified and that calendar is assigned to each resources