You should never modify your schedule once you published it. Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy. Leave the old schedule untouched so that you can use it as a baseline. Good luck!
Member for
17 years 4 monthsHi Ronald, Thanks a
Hi Ronald,
Thanks a lot
Kannan
Member for
22 years 10 monthsKannan, You should never
Kannan,
You should never modify your schedule once you published it. Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy. Leave the old schedule untouched so that you can use it as a baseline. Good luck!