P3 data saving before new updating

Member for

17 years 4 months

Hi Ronald,

Thanks a lot

Kannan

Member for

22 years 10 months

Kannan,

 

You should never modify your schedule once you published it.  Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy.  Leave the old schedule untouched so that you can use it as a baseline.  Good luck!