hi, if u hv any guide book .. pl send me one for same updating in p3 by saving target file. by the way also tell me wat are d ways to prepare a delay analysis using p3 module.
1. Tools update progress which automatically updates the schedule
2.Another one is manually as you said .Where one can plug actual start dates , physical completion form the field and actual finish date if the activity gets completed
what are you looking in the question how to make baseline ?
Member for
15 years 7 monthshi, if u hv any guide book ..
hi, if u hv any guide book .. pl send me one for same updating in p3 by saving target file. by the way also tell me wat are d ways to prepare a delay analysis using p3 module.
my email - raja_ghosal8888@rediffmail.com
Regards,
Member for
16 years 11 monthsRE: how to update p3 progress
Hi Zex
You can update in 2 ways
1. Tools update progress which automatically updates the schedule
2.Another one is manually as you said .Where one can plug actual start dates , physical completion form the field and actual finish date if the activity gets completed
what are you looking in the question how to make baseline ?