how to update p3 progress

Member for

15 years 7 months

hi, if u hv any guide book .. pl send me one for same updating in p3 by saving target file. by the way also tell me wat are d ways to prepare a delay analysis using p3 module.

my email - raja_ghosal8888@rediffmail.com

Regards,

Member for

16 years 11 months

Hi Zex



You can update in 2 ways



1. Tools update progress which automatically updates the schedule



2.Another one is manually as you said .Where one can plug actual start dates , physical completion form the field and actual finish date if the activity gets completed



what are you looking in the question how to make baseline ?