Primavera Project Planner - P3 Member for 20 years 7 months Member for 20 years 7 months Submitted by Rick Aquino on Mon, 2010-06-28 01:19 Permalink RE: Weighbridge construction Dear Shahab, Thank you very much for sharing it, Gratitude! Rick Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 11:19 Permalink RE: Weighbridge construction Mike, These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so. Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 11:18 Permalink RE: Weighbridge construction Hellow Mike Yes I was working on them thanks. 1. Crash Barrier 1 day 2. Cable routing 2 days 3. Ramp may require only 5 days. Can give u detail tommorrow Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-06-27 10:58 Permalink RE: Weighbridge construction Hi Shahab You forgot the drainage. It will also need a cabin for the operator and the calibration kit. Best regards Mike Testro Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 10:22 Permalink RE: Weighbridge construction Hi I think these may help you. Excavation 2 days PCC 15 days Ramp 10 days Installation of mechanical eqpts 10 days Electrical installations 7 days All in all they shld finish within 40 -45 days Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2010-06-12 15:27 Permalink RE: Weighbridge construction Hi Rick Its just a box in the ground with some kit in it. Whats your problem? Best regards Mike Testro Log in or register to post comments
Member for 20 years 7 months Member for 20 years 7 months Submitted by Rick Aquino on Mon, 2010-06-28 01:19 Permalink RE: Weighbridge construction Dear Shahab, Thank you very much for sharing it, Gratitude! Rick
Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 11:19 Permalink RE: Weighbridge construction Mike, These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so.
Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 11:18 Permalink RE: Weighbridge construction Hellow Mike Yes I was working on them thanks. 1. Crash Barrier 1 day 2. Cable routing 2 days 3. Ramp may require only 5 days. Can give u detail tommorrow
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-06-27 10:58 Permalink RE: Weighbridge construction Hi Shahab You forgot the drainage. It will also need a cabin for the operator and the calibration kit. Best regards Mike Testro
Member for 15 years 10 months Member for 15 years 10 months Submitted by Shah Syed Zaheer on Sun, 2010-06-27 10:22 Permalink RE: Weighbridge construction Hi I think these may help you. Excavation 2 days PCC 15 days Ramp 10 days Installation of mechanical eqpts 10 days Electrical installations 7 days All in all they shld finish within 40 -45 days
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2010-06-12 15:27 Permalink RE: Weighbridge construction Hi Rick Its just a box in the ground with some kit in it. Whats your problem? Best regards Mike Testro
Member for
20 years 7 monthsRE: Weighbridge construction
Dear Shahab,
Thank you very much for sharing it,
Gratitude!
Rick
Member for
15 years 10 monthsRE: Weighbridge construction
Mike,
These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so.
Member for
15 years 10 monthsRE: Weighbridge construction
Hellow Mike
Yes I was working on them thanks.
1. Crash Barrier 1 day
2. Cable routing 2 days
3. Ramp may require only 5 days.
Can give u detail tommorrow
Member for
19 years 10 monthsRE: Weighbridge construction
Hi Shahab
You forgot the drainage.
It will also need a cabin for the operator and the calibration kit.
Best regards
Mike Testro
Member for
15 years 10 monthsRE: Weighbridge construction
Hi I think these may help you.
Excavation 2 days
PCC 15 days
Ramp 10 days
Installation of mechanical eqpts 10 days
Electrical installations 7 days
All in all they shld finish within 40 -45 days
Member for
19 years 10 monthsRE: Weighbridge construction
Hi Rick
Its just a box in the ground with some kit in it.
Whats your problem?
Best regards
Mike Testro