Weighbridge construction

Member for

20 years 7 months

Dear Shahab,



Thank you very much for sharing it,



Gratitude!



Rick

Member for

15 years 10 months

Mike,

These days all are latest bridges without pits. Do you hav a pit for your weight bridge I dont think so.

Member for

15 years 10 months

Hellow Mike

Yes I was working on them thanks.

1. Crash Barrier 1 day

2. Cable routing 2 days

3. Ramp may require only 5 days.



Can give u detail tommorrow

Member for

19 years 10 months

Hi Shahab



You forgot the drainage.



It will also need a cabin for the operator and the calibration kit.



Best regards



Mike Testro

Member for

15 years 10 months

Hi I think these may help you.



Excavation 2 days

PCC 15 days

Ramp 10 days

Installation of mechanical eqpts 10 days

Electrical installations 7 days

All in all they shld finish within 40 -45 days

Member for

19 years 10 months

Hi Rick



Its just a box in the ground with some kit in it.



Whats your problem?



Best regards



Mike Testro