Hi vinod



You can treat the updated schedule as target.Make sure the existing pro-gramme[Which you use for monitoring ] and target should not have same file name.Make sure your target and existing pro-gramme are in one folder

Member for

19 years

Hi Vinod,

Open the project that you wanted to save as target.

Select Tools->Project Utilities->Copy. Once copied, Select Tools->Project Utilities->Target, select the project copied.