You can treat the updated schedule as target.Make sure the existing pro-gramme[Which you use for monitoring ] and target should not have same file name.Make sure your target and existing pro-gramme are in one folder
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Mon, 2010-04-12 09:18
Member for
16 years 11 monthsRE: Updated prgram as baseline program
Hi vinod
You can treat the updated schedule as target.Make sure the existing pro-gramme[Which you use for monitoring ] and target should not have same file name.Make sure your target and existing pro-gramme are in one folder
Member for
19 yearsRE: Updated prgram as baseline program
Hi Vinod,
Open the project that you wanted to save as target.
Select Tools->Project Utilities->Copy. Once copied, Select Tools->Project Utilities->Target, select the project copied.
Note: Only 2 projects can be display at the same time. If already have 2, replace any one of them.