Adding more activities to base line schedule

Member for

20 years 11 months

Agree with Gary,



it is imperative that you rebaseline by including this new scope and this should be submitted for acceptance and then this will become your new baseline.



wondering what are the conditions of the contract...?



cheers



Waseem Saber

Member for

16 years 7 months

1) Copy ther approved baseline schedule,

2) update WBS, activitites, resources, schedule, logic, etc to reflect additional works

3) Make sure you understand & can defend any impact on the schedule for original scope arrising from the addition of the new works.

4) Issue new baseline schedule, manpower loading, cashflow forecasts, etc for approval