it is imperative that you rebaseline by including this new scope and this should be submitted for acceptance and then this will become your new baseline.
wondering what are the conditions of the contract...?
cheers
Waseem Saber
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Thu, 2009-04-16 03:51
Member for
20 years 11 monthsRE: Adding more activities to base line schedule
Agree with Gary,
it is imperative that you rebaseline by including this new scope and this should be submitted for acceptance and then this will become your new baseline.
wondering what are the conditions of the contract...?
cheers
Waseem Saber
Member for
16 years 7 monthsRE: Adding more activities to base line schedule
1) Copy ther approved baseline schedule,
2) update WBS, activitites, resources, schedule, logic, etc to reflect additional works
3) Make sure you understand & can defend any impact on the schedule for original scope arrising from the addition of the new works.
4) Issue new baseline schedule, manpower loading, cashflow forecasts, etc for approval