Changing Duration from Hour to Day in P6

Member for

16 years 3 months

edit users preferences thne Time units Tab 

durations format

choose day

Member for

7 years

Hi



Concerning  histogram in resource usage profile the Axis "Y" it written  EX: 2.50d,5.0d,... i need to change it into 2h,4h,6h,... 

if anyone can help

Thank you

Member for

17 years 3 months

Hi Arnold



I actually got the issue resolved thanks.



The problem was the P6.1(contractor) to P5(me) conversion. When using a friend’s P6.1 the duration was changed to days and worked just fine.



Thanks

Member for

17 years 3 months

Hi Arnold



Normaly you could change the duration by typing i.e 3 days. After changing the duration to days, the activities display duration in days but if you change original duration to 3 it is not 3 days but 3 hours.



I like P6 in some ways but in some ways it SUCKS..



Know P3 well though..

Member for

18 years 6 months

Hi Martin,



As far as I know, you can only change the hour to day is from user preferences as what you did.



By the way, what do you mean "when you enter durations it is still in hours"?



Arnold