Normaly you could change the duration by typing i.e 3 days. After changing the duration to days, the activities display duration in days but if you change original duration to 3 it is not 3 days but 3 hours.
I like P6 in some ways but in some ways it SUCKS..
Member for
16 years 3 monthsedit users preferences thne
edit users preferences thne Time units Tab
durations format
choose day
Member for
7 yearsHi Concerning histogram in
Hi
Concerning histogram in resource usage profile the Axis "Y" it written EX: 2.50d,5.0d,... i need to change it into 2h,4h,6h,...
if anyone can help
Thank you
Member for
17 years 3 monthsRE: Changing Duration from Hour to Day in P6
Hi Arnold
I actually got the issue resolved thanks.
The problem was the P6.1(contractor) to P5(me) conversion. When using a friends P6.1 the duration was changed to days and worked just fine.
Thanks
Member for
17 years 3 monthsRE: Changing Duration from Hour to Day in P6
Hi Arnold
Normaly you could change the duration by typing i.e 3 days. After changing the duration to days, the activities display duration in days but if you change original duration to 3 it is not 3 days but 3 hours.
I like P6 in some ways but in some ways it SUCKS..
Know P3 well though..
Member for
18 years 6 monthsRE: Changing Duration from Hour to Day in P6
Hi Martin,
As far as I know, you can only change the hour to day is from user preferences as what you did.
By the way, what do you mean "when you enter durations it is still in hours"?
Arnold