Primavera Project Planner - P3 Member for 17 years 5 months Member for 17 years 5 months Submitted by Brad Richey on Mon, 2008-06-30 14:00 Permalink RE: what is impact on schedule using negative Lag If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes. Member for 17 years 4 months Member for 17 years 4 months Submitted by Ahmad saeed on Sun, 2008-06-29 05:27 Permalink RE: what is impact on schedule using negative Lag Hi Salauddin, Using negative lags in the relationship has no effect on the schedule. you can change the relations from FS with -ve lag to SS with +ve lag. Hope that this will help. Log in or register to post comments
Member for 17 years 5 months Member for 17 years 5 months Submitted by Brad Richey on Mon, 2008-06-30 14:00 Permalink RE: what is impact on schedule using negative Lag If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes.
Member for 17 years 4 months Member for 17 years 4 months Submitted by Ahmad saeed on Sun, 2008-06-29 05:27 Permalink RE: what is impact on schedule using negative Lag Hi Salauddin, Using negative lags in the relationship has no effect on the schedule. you can change the relations from FS with -ve lag to SS with +ve lag. Hope that this will help.
Member for
17 years 5 monthsRE: what is impact on schedule using negative Lag
If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes.
Member for
17 years 4 monthsRE: what is impact on schedule using negative Lag
Hi Salauddin,
Using negative lags in the relationship has no effect on the schedule.
you can change the relations from FS with -ve lag to SS with +ve lag.