what is impact on schedule using negative Lag

Member for

17 years 5 months

If you change the relations from FS with -ve lag to SS with +ve lag be sure to include a FF relationship between the same two items if you do not you may be finishing the successor before the predecessor completes.


Member for

17 years 4 months

Hi Salauddin,



Using negative lags in the relationship has no effect on the schedule.



you can change the relations from FS with -ve lag to SS with +ve lag.



Hope that this will help.