Anoon, you are right with that. It will function the same.



Albert, I think I don’t know of such way in P3. I hope others do and would tell us.



In order for me to make distinction between the target and the early bar, with both bearing the critical color on them,... I will just reduce the size of the target bar.. say from 5 to 2. This serves me best though...



Best regards,



Gerry

Member for

17 years 4 months

Thank you Gerry for your suggestion its possible for all none critical activity. but i just want to modify only the color of critical activity from red to any color without affecting early bar schedule.becouse any color i have chosen on critical the current schedule still the same. P3 v3.1 its my software version.

Member for

19 years 1 month

in addition to what Gerry had said, i remember there is an option to "display criticality on - you can choose between your baseline schedule and current schedule".

Member for

17 years 7 months

Hi Albert,



Do not show critical colors on your target bars.



Go to FORMAT, BARS, and on the DEFINE BARS pop-up, hi-light the TARGET BAR. Clear the check mark on the column CRITICAL. This will now show the color you have selected for the target bar.



To modify the color of the target bar, when are still on the DEFINE BARS pop-up, hi-light TARGET BAR and click the MODIFY button. In the MODIFY BAR DEFINITION pop-up, click on the bar color and select the color you like.



Cheers,