Instead of using the line tool, use the curtain tool (on the same toolbar) and you can set the width so it stands out more. You can also set it to start at a certain date and end at a certain date to bracket your period of review.
Other than these, you have to go to inserting objects.
Member for
17 years 6 months
Member for17 years6 months
Submitted by smithie johnny on Mon, 2008-05-05 02:57
Member for
19 years 7 monthsRE: Placing a line milestone in P3
Instead of using the line tool, use the curtain tool (on the same toolbar) and you can set the width so it stands out more. You can also set it to start at a certain date and end at a certain date to bracket your period of review.
Other than these, you have to go to inserting objects.
Member for
17 years 6 monthsRE: Placing a line milestone in P3
So i have been told to use the "Line Tool" under the "Attachment Tools".
It works well, apart from the fact you can only link it to a date and not an Activity.
Also is there a way to format this Line, so that it stands out more???
Help???
Member for
17 years 6 monthsRE: Placing a line milestone in P3
Or is there some way of placing a visual aid in the bar chart to show activities before and after this date?