Placing a line milestone in P3

Member for

19 years 7 months

Instead of using the line tool, use the curtain tool (on the same toolbar) and you can set the width so it stands out more. You can also set it to start at a certain date and end at a certain date to bracket your period of review.



Other than these, you have to go to inserting objects.

Member for

17 years 6 months

So i have been told to use the "Line Tool" under the "Attachment Tools".



It works well, apart from the fact you can only link it to a date and not an Activity.



Also is there a way to format this Line, so that it stands out more???



Help???


Member for

17 years 6 months

Or is there some way of placing a visual aid in the bar chart to show activities before and after this date?