Data date

Member for

21 years 9 months

Primavera reads days from midnight upto 1 minute before midnite, therefore if you input progress for a day, you should set the data date as the next day as this is a new day. Confused? Thik of it this way....



Day 1 starts today, client asks for report on todays work, we cannot progress upto day 1 as it is past tense therefore we use the next working day.



Still confused?

Member for

18 years 5 months

1st of April, as data entered is upto 31st March

Member for

18 years 9 months

Dear Kumar,

The Data date should be 1st April , since you have already updated progress upto 31st March, you should let the software schedule from the 1st of April.

regards

deb