Primavera reads days from midnight upto 1 minute before midnite, therefore if you input progress for a day, you should set the data date as the next day as this is a new day. Confused? Thik of it this way....
Day 1 starts today, client asks for report on todays work, we cannot progress upto day 1 as it is past tense therefore we use the next working day.
The Data date should be 1st April , since you have already updated progress upto 31st March, you should let the software schedule from the 1st of April.
Member for
21 years 9 monthsRE: Data date
Primavera reads days from midnight upto 1 minute before midnite, therefore if you input progress for a day, you should set the data date as the next day as this is a new day. Confused? Thik of it this way....
Day 1 starts today, client asks for report on todays work, we cannot progress upto day 1 as it is past tense therefore we use the next working day.
Still confused?
Member for
18 years 5 monthsRE: Data date
1st of April, as data entered is upto 31st March
Member for
18 years 9 monthsRE: Data date
Dear Kumar,
The Data date should be 1st April , since you have already updated progress upto 31st March, you should let the software schedule from the 1st of April.
regards
deb