Date format in P3

Member for

17 years 11 months

Correct! The problem here is your version differs from what others have. Sometimes, a very simple function can cause a little bit problem when you are a beginner!

Member for

18 years 5 months

I hav P3.0,



Just go to Format --> Dates.



U can select the required format.



Cheers,



Rav

Member for

18 years

It is P3.0 version. maybe there is no such function.



Thank you very much for your information which is very useful.

Member for

17 years 11 months

What is your version? In p3.1, We dont have the function showed by Nar

Member for

18 years

Excuse me, I can’t find the project tab from tools>options in P3.



Can you give me more hints?

Member for

18 years 1 month

try this one

tools>option>project tab--- change date format at Dates

cheers

Member for

18 years





I mean that when I open P3,Format , then date, I just can choose dates in number format (e.g. 16112007) and I can’t choose the date format like 16Nov2007. Do you know why is that?



Thank you

Member for

17 years 11 months

Hi Sum,

Can you detail more?

Member for

18 years

Hi all



I also click* Format>dates. I just select the date format 080123. But I can’t select the date format 23 JAN 08 in my P3 programme. Do you know why?



Thank you





Mercer

Member for

18 years 5 months

Thanx James,



How Sometime one can forget the basic things and make the problem look worse ?



:-)

Member for

18 years 2 months

Raviraj



yes, it is possible.



*click* Format>dates



In the dialog box is a selection of date styles. the one you want, I think, is the bottom one



I believe this is view specific so you will need to change it in each of your views



R



James