Dear Mr. Hady,

This can be achived with a WBS activity.

Put the activities A , B and C all in one WBS level ( Task activities ) , activity D should be assigned a WBS activity also in the same level.Now from the cost form insert cost for activities A,B and C , u will get all wrapped up in activity D

HTH