Primavera Project Planner - P3 Member for 18 years 9 months Member for 18 years 9 months Submitted by Pranab Kumar Deb on Mon, 2007-05-28 23:53 Permalink RE: Cost all n 1 Dear Mr. Hady, This can be achived with a WBS activity. Put the activities A , B and C all in one WBS level ( Task activities ) , activity D should be assigned a WBS activity also in the same level.Now from the cost form insert cost for activities A,B and C , u will get all wrapped up in activity D HTH Deb Log in or register to post comments
Member for 18 years 9 months Member for 18 years 9 months Submitted by Pranab Kumar Deb on Mon, 2007-05-28 23:53 Permalink RE: Cost all n 1 Dear Mr. Hady, This can be achived with a WBS activity. Put the activities A , B and C all in one WBS level ( Task activities ) , activity D should be assigned a WBS activity also in the same level.Now from the cost form insert cost for activities A,B and C , u will get all wrapped up in activity D HTH Deb
Member for
18 years 9 monthsRE: Cost all n 1
Dear Mr. Hady,
This can be achived with a WBS activity.
Put the activities A , B and C all in one WBS level ( Task activities ) , activity D should be assigned a WBS activity also in the same level.Now from the cost form insert cost for activities A,B and C , u will get all wrapped up in activity D
HTH
Deb