Dear A.S.SHUKLA



Program is written in Visual Basic and uses the ODBC drivers to read the P3 database can calculate the percentage on each activity that is a WBS activity type based on the option set in Tool, Summarization.



The percentage on the activity with a WBS activity type will then match the percentage calculated in the summarised band when grouped by WBS.



Regards,



Frank

Member for

24 years 6 months

P3 3.1 has an option to summarize percentage complete weighted by Duration, Resource Units or Cost. The WBS activity type always uses duration as per the Primavera help file.



However we have written an program that uses the P3 option setting to determine how to calculate the summarise percentage on the WBS activity types and update every WBS activity type in the schedule. The WBS activity type percentage will then match the percentage in the summarised band when grouped by WBS. Installs as a tool like Project Check-in/Check-out in the Tools menu.



Used by Defence contractors as they MUST use WBS activity types for their CSSR /CSCS interfaces from P3 3.1



HTH



Frank Borcherdt

Member for

20 years 8 months

Yes, that’s exactly what I mean. You need to do this double work if you are working in P3 3.1. P5 can do it automatically.

Member for

18 years 6 months

Bijaya,



Correct me if I am wrong,



What you are trying to say that we have to convert the % complete of of all different items into the manhours earned and adding up the earned manhours will give us the % complete for the Hammock.



This is how we do and the progress of P3 to keep the schedule as realistic as possible. Although it is double work.





Regards,





Ashraf

Member for

20 years 8 months

Physical Progress cannot be rolled up. Just to illustrate - how can you add or roll up 25% of drawings and 50% excavation physically? It is not possible physically. However if you have cost loaded both the activities, you can then roll up the earned value cost of any odd types of activities together and calculate % complete for your hammock or roll up. In P3e an above you can do it however in P3 3.1, since there is only one type of % complete, you will have to do this calculation out of P3 (in spreadsheet for example).

Member for

19 years 4 months

All,



How to input/calculate Physical Progress on the hammock activities.



Seems to me that the progress is calculated based on duration Not physical.



Can you help me.





Thanks

Member for

20 years 8 months

Yes, I meant to say WBS. I was writing the posts without even checking it in software. And activiity type WBS is available in both P3 3.1 and P5. In a number of situations in the project, work is broken down to details but it is not practical to load resources at those micro levels of activities. WBS type of activities then come handy at that moment - you can assign resource to WBS activity only (which is hammock or summary of a group of activities). When you progress the individual activities, the WBS activity gets progressed automatically and you can get earned value and other calculations at that level easily. You cannot do this in ordinary hammock activity which is merely a time from start of an activity to finish of another activity.

Member for

18 years 5 months

Thanks Rodel,



Also the difference between WBS and Hammock is that, WBS activity can be assigned to group of activities having common WBS level. Wherein, hammocks can be assigned to any group of activities.



But, typically both share the same purpose giving start and finish dates for the assigned group of activities



Cheers,



Raviraj

Member for

19 years

There is no WBS hammock but WBS is act like hammock. I think what he mean is WBS as WBS summary in P3e or P5. If you assign activity as WBS, you don’t need to link your activity where hammock required to define the link SS to first activity and FF to last activity same as level of effort in P3e/P5. When activities are assign as hammock or WBS, the progress was updated automatically when you update the activities under the hammock or WBS.

Regards,
Rodel

Member for

18 years 9 months

ya bijaya same here , can u confirm if in p3 v3.1 there is wbs hammock as well

regards

deb

Member for

19 years 10 months

IN P3 V-3 , THERE ARE ONLY HAMMOCKS ONLY IN TYPE OF TASKS . I DID NOT FIND ANY WBS HAMMOCK

Member for

20 years 8 months

Deb,



Check the Activity type - you will find different options including milestones, tasks, hammock and WBS hammock. All you need to do is create an activity with activty type WBS hammock. Then this activity will roll up all the activities which are assigned the same WBS.

Member for

18 years 9 months

hello bijaya,

i needed some more information on this how can be activity assigned as WBS hammock.

regards

deb

Member for

18 years 10 months

That is what I thought but was just checking to make sure if there was an easier way. Thanks for your assistance.

Member for

20 years 8 months

Not quite.



You can roll up a series of activities as WBS hammock. You don’t need to make any link to WBS hammock (unlike hammock activity where you need to give SS and FF link).



When you update your individual activities with progress, the WBS hammock activity gets updated automatically. It is this way not the other way.