How to change the starting date of a project

Member for

11 years 7 months

after Creating the projet.Close the entore priamvera and open it again.Clik our projeCt whih one to Change.

then replae on dates(before entering to the projet)

its helpfull only if before the baseline reation.

 

 

 

Member for

16 years 3 months

wrong section of forum

Member for

12 years 6 months

Let me clear ur doubt in Primavera Latest Version 8.2

 

Open Primavera ! Select  " FILE" close all the Projects which are Opened 

Go to Enterprise Select the Project for which u want to change the start date of the Project 

Right Click on the Project Select option "Project Details" from Down

Select it twice if u did not get the details in first attempt 

then u can able to see the--- show bottom view tabs .. 

in that select the tab " DATES" and change the date what ever u want .. that's it ur done 

 

if u did not follow this process directly changed the actual start of the first activity it will be converted in to Constraint. 

Member for

22 years 5 months

Javier



If I understood you correctly what you want is to have a new schedule that will show a delay of a month, if this is the case you should backup your original schedule (for reference) then adjust the current schedule start date to your new start date then change your data date equal to your new start date and reschedule it... for adjusting the reference start date line kindly refer to mr. Paul’s suggestion...



HTH



Christian

Member for

19 years

Thank you Paul.

I did what you suggested, but only the reference start date line was moved and the other details remained as before.

I don’t want to keep the original programme as reference (with a month of delay), the idea is to have a new programme that will start with a month of difference from the original plan.

Maybe I have to do another step.

If you have more suggestions I’ll be glad to try them.

Member for

24 years 6 months

Select File, Project Overview and set a new start date.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting