If I understood you correctly what you want is to have a new schedule that will show a delay of a month, if this is the case you should backup your original schedule (for reference) then adjust the current schedule start date to your new start date then change your data date equal to your new start date and reschedule it... for adjusting the reference start date line kindly refer to mr. Pauls suggestion...
HTH
Christian
Member for
19 years
Member for19 years
Submitted by Javier F. Via Giglio on Sat, 2006-10-28 13:21
I did what you suggested, but only the reference start date line was moved and the other details remained as before.
I dont want to keep the original programme as reference (with a month of delay), the idea is to have a new programme that will start with a month of difference from the original plan.
Maybe I have to do another step.
If you have more suggestions Ill be glad to try them.
Member for
11 years 7 monthsafter Creating the
after Creating the projet.Close the entore priamvera and open it again.Clik our projeCt whih one to Change.
then replae on dates(before entering to the projet)
its helpfull only if before the baseline reation.
Member for
16 years 3 monthswrong section of forum
wrong section of forum
Member for
12 years 6 monthsLet me clear ur doubt in
Let me clear ur doubt in Primavera Latest Version 8.2
Open Primavera ! Select " FILE" close all the Projects which are Opened
Go to Enterprise Select the Project for which u want to change the start date of the Project
Right Click on the Project Select option "Project Details" from Down
Select it twice if u did not get the details in first attempt
then u can able to see the--- show bottom view tabs ..
in that select the tab " DATES" and change the date what ever u want .. that's it ur done
if u did not follow this process directly changed the actual start of the first activity it will be converted in to Constraint.
Member for
22 years 5 monthsRE: How to change the starting date of a project
Javier
If I understood you correctly what you want is to have a new schedule that will show a delay of a month, if this is the case you should backup your original schedule (for reference) then adjust the current schedule start date to your new start date then change your data date equal to your new start date and reschedule it... for adjusting the reference start date line kindly refer to mr. Pauls suggestion...
HTH
Christian
Member for
19 yearsRE: How to change the starting date of a project
Thank you Paul.
I did what you suggested, but only the reference start date line was moved and the other details remained as before.
I dont want to keep the original programme as reference (with a month of delay), the idea is to have a new programme that will start with a month of difference from the original plan.
Maybe I have to do another step.
If you have more suggestions Ill be glad to try them.
Member for
24 years 6 monthsRE: How to change the starting date of a project
Select File, Project Overview and set a new start date.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au