Budgeted quantity filter

Member for

20 years 3 months

I’ve tried both, but it looks like it had to be on Activity instead of Resource/cost

And all resources were added at the same time long before I tried this filter.

Member for

22 years 11 months

Did you set up your CDI as an activity or resource ?

Member for

20 years 5 months

do u already include your carpenter in resource? u should include all the resource account then u can add the resource using global change, if not this global change could not transfer as u instruct.