Primavera Project Planner - P3 Member for 20 years 3 months Member for 20 years 3 months Submitted by Yves Trudel on Wed, 2005-08-03 08:12 Permalink RE: Budgeted quantity filter Ive tried both, but it looks like it had to be on Activity instead of Resource/cost And all resources were added at the same time long before I tried this filter. Member for 23 years Member for 23 years Submitted by Steven Oliver on Wed, 2005-08-03 07:18 Permalink RE: Budgeted quantity filter Did you set up your CDI as an activity or resource ? Member for 20 years 5 months Member for 20 years 5 months Submitted by Raja Izat Raja… on Wed, 2005-08-03 05:56 Permalink RE: Budgeted quantity filter do u already include your carpenter in resource? u should include all the resource account then u can add the resource using global change, if not this global change could not transfer as u instruct. Log in or register to post comments
Member for 20 years 3 months Member for 20 years 3 months Submitted by Yves Trudel on Wed, 2005-08-03 08:12 Permalink RE: Budgeted quantity filter Ive tried both, but it looks like it had to be on Activity instead of Resource/cost And all resources were added at the same time long before I tried this filter.
Member for 23 years Member for 23 years Submitted by Steven Oliver on Wed, 2005-08-03 07:18 Permalink RE: Budgeted quantity filter Did you set up your CDI as an activity or resource ?
Member for 20 years 5 months Member for 20 years 5 months Submitted by Raja Izat Raja… on Wed, 2005-08-03 05:56 Permalink RE: Budgeted quantity filter do u already include your carpenter in resource? u should include all the resource account then u can add the resource using global change, if not this global change could not transfer as u instruct.
Member for
20 years 3 monthsRE: Budgeted quantity filter
Ive tried both, but it looks like it had to be on Activity instead of Resource/cost
And all resources were added at the same time long before I tried this filter.
Member for
23 yearsRE: Budgeted quantity filter
Did you set up your CDI as an activity or resource ?
Member for
20 years 5 monthsRE: Budgeted quantity filter
do u already include your carpenter in resource? u should include all the resource account then u can add the resource using global change, if not this global change could not transfer as u instruct.