Bogus EF dates...

Member for

20 years 8 months

Go to Project Overview > check Project Must Finish By. If you imposed any finish date constraint, remove it and re-calculate the schedule.



Regards.

Member for

20 years 4 months

No, I checked all that.



It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.

Member for

22 years 10 months

Do you have an Expected Finish constraint posted for that activity?